Information
Digital ID
man000172-069
Permalink
4 LAS VEGAS LAMP AND WATER COMPANY TABLE G Fixed Capital SUMMARY TOTAL Estimated 12/51/48 12/51/49 12/51/50 1/ Original Cost Present-Day Cost $ 652,552 872,000 $ 805,011 $ Or, 075,204 1 q j J 12/51/49 Original Cost 12/51/49 Present-Day Cost Sparling meter 8 ” $ 842 $ 1,545 Water pump 255 450 W. I. pipe 5” 444 1,165 Welded steel pipe 6 " 14,425 19,889 C. I. pipe 2 " 575 575 4” 87,564 151,981 6 » 551,009 456,278 8 ” 200,497 281,106 1 0 " 49,798 58,000 1 2 " 88,694 110,057 16" 904 1,524 Office furniture 552 865 Chevrolet sedan 1,059 1,685 Oldsmobile " 2,725 2,675 Shop building, frame 285 1,078 Equipment & tools 507 958 Chevrolet truck 1,779 1,860 International truck 1,759 1,759 Total $805,011 $1,075,204 945,000 1/ Estimated costs as of December 51, 1950, are equal to 12/51/49 amounts plus estimated net A ’S & B ’s for 1950 in the amount of $140,000.