V 2* Mr* R.L® Adamson: Item 4, Fire Pump House and Fire Lines ( Contd.) Fire pump base has been placed but no other work completed on pump house except forms fo r floor* The la s t advice from Worthington Pump Co* is that the fi r e pump is scheduled to be shipped from Harrison, N*J* on August 31st* Item 9> Power Lines* Power lin e has been completed to Pump House site* Information from Store Dept* indicates that transformers have been promised fo r shipment from the factory on July 1 5 , 1946. G E N E R A L : Mr* Pegraa, Supt* fo r McNeil Housing, was instructed yesterday, July ISth, to place top on valve box Just west of U* P* main lin e and also replace barb wire fence along the Wollman property and along 0*P* right-of-w ay. He was also instructed to replaoe 2 posts in Opaco Lumber Co* fence which were removed at time ditch was dug under fenoe* L • R • J