Information
Digital ID
upr000178-047
Permalink
W 2>l-65 Hr, L, A. Whites Tour letter September 12, file BP 9-2-4, regarding close-out of charges to W,0, 639, Installation of Water Heine in the Scotch Eighty, Further review of this subject develops that you are right and we are wrong. Of the 6 tees ordered for this Job, 1 was returned to our H,0«B, stock, 1 was used for a fire hydrant and the remaining 4 should have been charged to investment in the main line. After deducting the value of tho second tee transferred to our M,o.m account, H9*5®# the correct charge to investment account should be $4,600,45, After adding 10# for supervision installation of pipe plus firo hydrant and fittings, tho total cost to sub-divider would be $5,086,66, leaving a refund of $843,34 duo Hr, Kunkel from the $5,030 advanced on tho estimated cost. Will you kindly correct your records accordingly. Las Vegas — September 14, 195b A. H, Folger